James B. Atkins, FAIA and Grant A. Simpson, FAIA
It may surprise some people to hear that the architect's
documents cannot be used for construction. Many are of the
opinion that the architect prepares the documents and gives
them to the contractor, and the contractor takes them and
builds the building from the information contained therein.
But nothing could be farther from the truth.
Then why does the architect place on the documents "Issued
for Construction"? Although common practice, this phrase,
when affixed to the architect's drawings, can be
misunderstood. Nevertheless, this phrase is better than
labeling them "100% CD Set," "Final Construction
Documents," or something equally misleading. The documents
are not issued for construction per se, but instead, they
are issued to facilitate construction by expressing the
design concept. The documents do not contain sufficient
information to construct the project, and much more
information is required before the work can be done. In
fact, the architect's documents only represent information
sufficient for the contractor to begin "the contractor's
required work." The contractor's work includes the
preparation of detailed construction documents, more
commonly known as shop drawings and submittals, coordination
drawings, and alternate sketches, all of which set out the
specific and final details required for procuring and
placing the finished work. By contrast, drawings by
architects merely reflect the finished design of the work.
This article will examine the role contractor-provided
construction documents play in the construction process,
along with the other information that is required to
complete a project. It will examine why the design
professional's documents cannot be used as the actual
documents for implementing construction, and it will explore
what information is actually used, why it is used, and from
where it originates.
The Design Concept
As defined by Webster's, the term "concept" is "an
abstract or generic idea." This definition makes it clear
that a concept is not a specific or finite solution with
tangible parameters.
The limited content of the architect's drawings is more
explicitly addressed in The Architect's Handbook of
Professional Practice, 13th Ed., in Section 13.4, "Construction
Documents Production" wherein it states: "It is
important that all parties understand that construction
documents are not intended to be a complete set of
instructions on how to construct a building. Construction
means, methods, techniques, sequences, procedures, and site
safety precautions are customarily assigned as
responsibilities of the contractor to give the contractor
full latitude in preparing bids and carrying out the
construction phase."
Similarly, Section 3.12.4 of AIA document A201, General
Conditions of the Contract for Construction states that the
inherently conceptual nature of construction documents
prepared by architects and the related responsibilities of
the contractor/construction manager for detailed submittals
and shop drawings: "Shop Drawings, Product Data, Samples
and similar submittals are not contract documents. The
purpose of their submittal is to demonstrate for those
portions of the work for which submittals are required by
the contract documents the way by which the contractor
proposes to conform to the information given and the design
concept expressed in the contract documents."
Moreover, Section 3.12.6 of A201 addresses the
relationship of the contractor's submittals and shop
drawings to the contractor's plan for procuring and
placing the work: "By approving and submitting Shop
Drawings, Product Data, Samples and similar submittals, the
Contractor represents that the Contractor has determined and
verified materials, field measurements and field
construction criteria related thereto, or will do so, and
has checked and coordinated the information contained within
such submittals with the requirements of the Work and of the
Contract Documents."
This powerful language explicitly requires the contractor
to first check each submittal and coordinate it with field
conditions and the requirements of the work before
submitting it to the architect or engineer to review for
conformance with "the information given and the design
concept expressed in the contract documents." MasterSpec,
a product of the AIA and the industry standard for
construction specifications, devotes an entire section on
project management and coordination (Section 01310, "Project
Management and Coordination"). This description of the
content of coordination drawings explicitly requires them to
be original, detailed comparisons of the various trades, and
it recognizes that the architect's drawings will likely be
in conflict with selected equipment and required clearances
to the extent that coordination is necessary and advisable.
The contractor is specifically directed to provide sketches
for resolution of such predictable conflicts.
Furthermore, A201 places the contractor in charge of
determining how the work will be divided into separate
trades, how the work will be bid and purchased, and how the
purchased products and systems will be coordinated and
incorporated into the completed work. A201 also charges the
contractor with ensuring that the work will be in
conformance with the design concept expressed in the
contract documents.
Although AIA document A201 makes the lines of
responsibility for planning the implementation of the work
abundantly clear, and MasterSpec sets out specific
requirements for accomplishing the task, some assert that a
contractor's change order is justified whenever
information is not specifically expressed in the architect's
documents. As a result, contractors routinely make these
assertions through the RFI process and inevitably write
change orders to add information to the architect's
documents—information never rightfully required or
intended to be there in the first place.
For example, an architect has indicated "recessed fire
extinguisher cabinet" on an interior wall elevation in the
architectural drawings. While no specific dimensions are
indicated for the cabinet location, the specifications list
several acceptable manufacturers for the cabinet. Still, the
contractor submits an RFI: "Please provide detail for
cabinet framing in wall."
In this instance the contractor should provide the final
answer since the size and mounting detail of a recessed fire
extinguisher cabinet varies with the manufacturer. The
architect could not have precisely detailed the installation
without knowing which manufacturer's cabinet was to be
used. Also, it is not necessary for the architect to provide
a framing detail because the manufacturer's literature
describes how the cabinet is to be installed. If the
architect answers the RFI with a framing detail, it is
likely that the contractor will ask for additional money for
the newly detailed framing, alleging that scope was added to
the drawings. If the architect doesn't answer the RFI he
risks being accused of not being responsive. One appropriate
response is to suggest that the contractor honor the
manufacturer's instructions for the product they have
selected.
Benefits of Conceptual Design Drawings
AIA documents have expressly indicated for many years
that the architect's drawings are conceptual, and they
have required contractors to represent through their review
of shop drawings that they have "determined and verified
materials, field measurements and field construction
criteria." These actions naturally preclude "scaling"
the design drawing directly by attempting to determine
dimensions from the drawings with the use of an architect's
ruler.
In the 1980s, Gyo Obata, FAIA, one of the founding
fathers of Hellmuth Obata and Kassenbaum Architects (HOK),
decided to produce construction drawings in freehand, thus
emphasizing their conceptual nature. This forced the
contractors to rely on their work plan and the skills of
their trades to produce shop drawings to demonstrate how
they intended to "conform to the information given and the
design concept expressed in the contract documents."
Although considered by some to be extreme at the time,
Obata did not remove any usable information from his
documents. He merely added a human factor to his line work
that expressed the information in its simplest and most
obvious form, while at the same time underscoring the
reality that the architect's documents are conceptual. By
contrast, today's computerized document production does
little to reinforce the conceptual nature of design
drawings. While computers bring a high level of consistency
and efficiency to the architect's work, design drawings
rendered via computer are so crisp and precise as to appear
to have the precision of a shop drawing.
As is obvious to most architects, there are many benefits
to the use of conceptual design drawings in the construction
process. Some of these benefits are:
-
Promotes competition. Multiple acceptable
manufacturers allow the contractor to obtain the best price
or best delivery schedule. It is generally acknowledged that
a single source specified product will be more expensive
because of the lack of competition, and that is why it is
unlawful on public projects in many states.
-
Provides for the latest technology. A manufacturer's
product may undergo model and specification changes after
the project is designed and before the work is installed. A
good example is radiology equipment where specifications and
features change almost monthly and medical technologists and
radiologists desire the latest model for their facility. The
architect's conceptual design allows for product
procurement with more recent upgrades and developments.
-
Allows the trade to determine the final
configuration. While architects have a general familiarity
with many products, the trade contractor is the expert,
knows the product best and is more capable of determining
its ultimate design configuration.
-
Places responsibility for means and methods with an
experienced provider. Much like the designer's expertise
that is accrued from years of experience, the contractor's
expertise in the latest construction techniques and how
products and buildings go together is a career endeavor. The
contractor knows best how to develop a plan for making the
design concept a built reality.
The Contractor's Plan
The contractor's plan for procuring and placing the
work is not always entirely visible to the project team.
Although the contractor is required by the construction
contract to submit shop drawings, produce coordination
drawings, provide sketches to resolve dimensional conflicts,
along with being required to hold pre-installation
conferences – all of which the architect should be aware
of and may attend – for the most part the contractor's
work plan is transparent.
Components of the contractor's plan for the work are
addressed in Guidelines for a Successful Construction
Project, a joint publication of The Associated General
Contractors of America, the American Subcontractors
Association, and the American Specialty Contractors.
Pre-installation conferences and coordination of
subcontractors are addressed in Section D.2.a ("Guideline
on Communications"): "Coordination should be assured
through regular on-the-job meetings of the general
contractor's authorized project representative and the
on-site subcontractors' authorized project
representatives. Additional meetings may be required for
subcontractors whose work might interfere with another at a
given time."
This publication – formerly known as the Construction
Industry Survival Kit – also includes shop drawings and
submittal data and coordination drawings as primary topics
for discussion during the preconstruction conference. In
Section 6.1 ("Guideline on Preconstruction Conferences"),
under Topics for Discussion is Item 4: "Shop drawing and
sample submittal data including procedures for submittal,
review and approval…" And, Item 5 mentions coordination
drawings, which are referred to as interference and
composite drawings: "Requirements, if any, for
interference and/or composite drawings. Who initiates them
and what will be the order of progression of these drawings;
what is the impact on time for performing the work if
composite drawings are required?"
Through such publications, these major construction trade
associations acknowledge the role of the contractor in
developing and managing the work of coordinating the
subcontractors and providing composite coordination
drawings. They also recognize that time and planning will be
required to coordinate the subcontractors and prepare the
drawings necessary to facilitate constructing the work.
The contractor's plan is critical to the success of a
project, and it is developed and implemented by the
contractor's staff. Yet contractors sometimes reduce staff
as they seek to control general conditions costs or because
of pressure from owners to reduce expenses. Owners often
view these temporary facilities and services as transient,
with no sustaining benefit to the project. However, efforts
to reduce these costs can be misguided and may adversely
affect the project. Staff reductions are not made because
planning the work is not required, and consequently the work
must be provided by an alternate source. For survey and
layout services a common practice today is to buy layout
work from the individual trades performing the work. For
example, the plumber may be contracted to measure and layout
the locations of plumbing fixtures and equipment, and the
drywall contractor may be contracted to measure and layout
the walls. Under this scenario, where layout is not provided
as a general conditions service, the ability of the
contractor to confirm that the plumber's layouts are
compatible with the drywall contractor's layouts is
reduced. Typically, there are issues of coordination that
must be worked through between the two subcontractors. Since
the layout process has essentially bypassed the contractor's
supervision and control, it is not a part of the work plan,
and the subcontractor's source for layout information
apparently becomes only the architect's drawings.
Consequently, if there is a problem with coordinating the
layout between the subcontractors, the architect is often
mistakenly viewed as the responsible party.
However, according to Section 3.3.2 of AIA document A201,
the general contractor is solely responsible for the acts of
subcontractors and the coordination of their work: "The
Contractor shall be solely responsible for and have control
over construction means, methods, techniques, sequences and
procedures and for coordinating all portions of the Work
under the Contract..."
Coordination of the subcontractors by the contractor is
contractually required, and it is necessary for producing
properly placed work. Attempting to transfer the
responsibility for coordinating the work to the architect is
in conflict with the general conditions, the recommendations
of the leading trade associations, and although it may be a
common occurrence, it is not good construction practice.
The issue of pressuring contractors to reduce their
general conditions costs has seemingly played a part in
causing layout and coordination of the work by the
contractors in the field to become a vanishing art. The act
of developing a work plan, working with and coordinating
subcontractors and answering their questions has instead
evolved into an intensive RFI exchange often designed to
force the architect to provide some or all of the contractor's
field coordination services under duress. This act of
conscripting the architect or engineer is inherently
unsuccessful because they do not possess the contractor's
skills or contractual authority, and they do not provide
supervision. In the construction process there is simply no
substitute for the contractor's work plan.
The following RFI reflects the occasional passive nature
of how a contractor might attempt to conscript the services
of a architect: "Embeds for the roof screen wall support
column bases were set per unapproved shop drawings in the
interest of schedule. Please provide a detail for attaching
the column base plates with drilled epoxy inserts."
The contractor should have engaged an engineer to design
a correction to his placement mistake and proposed an
alternate sketch for the engineer of record to review as
MasterSpec requires. Nevertheless, the design team, in an
effort to assist in resolving the problem, responded by
sending an Architect's Supplemental Instruction (ASI) with
a detail for the inserts as requested. At the end of the
project, adding insult to injury, the contractor submitted
additional costs in a change order request for "providing
inserts per the architect's revised detail" that was
attached to the ASI, alleging that the detail was not the
most cost effective solution.
Conceptually Equal but Nominally Different
Both the architect's drawings and the contractor's
procurement and placement plan, which includes submittals
and shop drawings, are affected by the proprietary nature of
the specific materials and systems that the contractor
decides to purchase. In the absence of a sole source
specification, the architect cannot be expected to know
exactly which suppliers, manufacturers, or subcontractors
the contractor will select to include in the project. The
proprietary nature of today's market dictates that one
vendor's product will not exactly match another vendor's
product. Thus, the architect details the concept of an
installation and specifies the products or systems
advertised or known to be conceptually equal in quality. The
contractor is responsible for determining and defining
specifically how the conceptually equal but nominally
different products or systems that have been chosen for use
in the project will be incorporated into the work.
An example of a conceptually equal but nominally
different product can be found in the case of two popular
manufacturers of metal clad wood windows. Both Pella and
Andersen manufacture a wood window nominally sized 3' wide
by 5' high. However, the actual window provided by Pella
is 3' 1" wide by 4' 11" high, and the window
provided by Andersen is 2' 11H" wide by 4' 11H"
high.
Although the windows are of slightly different sizes, the
differences do not invalidate the concept of a 3' by 5'
window. Thus, without advance knowledge of exactly which
window the contractor will propose to buy, the architect can
approximately, but not exactly, represent in the design
documents what is required for the project. The
subcontractor then indicates in a submitted shop drawing
exactly how the selected window will be incorporated into
the work. The shop drawing, although it is not a "contract
document," becomes the document that is actually used for
construction. The architect's documents, since they are
conceptual, are not and cannot be the actual documents from
which construction is performed.
In another example, the conceptually equal but nominally
different nature of the final product to be provided is
actually of little concern to the architect, provided the
contractor coordinates the work of the subcontractors.
RFI Question: Fire/smoke dampers have been approved as
120 volt. The security system subcontractor has requested
permission to change these dampers to 24 volt. Will this
change be acceptable?
Engineer's Response: 120 volt or 24 volt is acceptable.
Subcontractors shall coordinate per contract.
As long as the dampers are coordinated and function with
all related systems, they will be in compliance with the
design concept.
The Purpose of the Architect's Dimensions
The purpose of the dimensions given in the architect's
drawings is to define the limits of and provide guidance for
placement of the elements of the work. If there is a
category of information provided in an architect's
drawings that must be used directly during the construction
process, it is likely to be dimensional information.
Nevertheless, the architect's dimensions must be
thoroughly examined and verified by the contractor preparing
the plan for procuring and placing the work because of the
variables in available products and construction techniques.
Therefore, the dimensions provided by the architect are
presented only in support of the design concept. Column
grids and building limits may be presented and used
literally as long as they have been confirmed by the
contractor's surveyor. However, standard convention
dictates that the architect may use certain nominal
dimensions that the contractor must interpret in actual
terms. For example, an 8" concrete masonry unit is
actually 7L" tall, and a 2x4 wood framing member is
actually 1H" by 3H".
Dimensions are also impacted by nominal proprietary
differences as in the case of the window size example given
above, or in the case of small differences in the actual
dimensions of kitchen appliances, plumbing fixtures and
accessories, floor tile, elevators and many other products.
These nominally differing dimensions, when they have a
critical impact on the layout of the building must be
highlighted in submittals, resolved through the RFI process,
or in most cases merely coordinated by the contractor or
subcontractor on site.
A good example of such a condition is pipe penetrations
in the building structural frame. The specifications often
require "sleeve layout drawings" to be submitted with
the structural shop drawings. The contractor is in the best
position to determine specifically where the sleeves for the
piping can be placed so as to not interfere with critical
structural members such as reinforcing steel or
post-tensioning tendons, or with the contractor's
provisions for constructability. The architect need not be
concerned about the precise location of the sleeve as long
as it falls within a wall or chase and meets the
requirements of the design concept.
Convention and common sense also allows that some
building elements may simply be "conceptually indicated"
but not actually dimensioned. Building elements often
indicated without dimensions commonly include doors
occurring in a long run of wall, electrical outlets whose
specific location is not critical, and other such elements.
The final "nominal" location of these building elements
is rightfully left to the discretion of the contractor.
How It Is Supposed To Work
When things go the way they are supposed to, the
architect's interaction is essentially one of answering
questions about design intent and possibly issuing a few
supplemental instructions. The contractor significantly
marks up submittals, and pre-installation conferences are
held at the contractor's request instead of because they
are required in the specifications. If all went as intended,
a project would go something like this:
-
architect designs project and issues design drawings
(drawings locate, specifications establish quality);
-
contractor develops plan for procuring the work and
allocates work among trades;
-
contractor and trades develop a plan for placing the
work and prepare composite coordination drawings and
alternate sketches;
-
trades prepare submittals and submit to contractor;
-
contractor coordinates trade submittals with the plan
for the work, marks up and approves submittals and submits
to architect;
-
architect reviews submittals for conformance with
design concept;
-
contractor and trades construct with approved
submittals;
-
contractor issues RFIs for questions that cannot be
answered from the information given or for questions about
discrepancies in the architect's documents; and
-
the architect responds to RFIs with answers to
questions.
If a project was indeed constructed as the AIA documents
anticipate, there would be less paperwork, fewer meetings,
and fewer conflicts and disagreements. There may be higher
general conditions costs to cover the contractor's
necessary labor, but there would be fewer coordination
issues, fewer reimbursable expenses for the owner to pay,
and a shorter period to close out the project. Although the
contractor's plan for procuring and placing the work is
not a frequent topic of conversation around the job site or
in the project meeting, there are contractors that actually
prepare such a plan and execute it as the AIA and the
leading construction trade associations recommend. The
telltale signs are marked-up trade submittals, detailed
coordination drawings, fewer RFIs, more installation
conferences, and less correspondence in general.
Conclusion
Contractor-provided construction documents are essential
for constructing a project, and it is evident that the
architect's drawings alone cannot be used because they are
conceptual in nature and inherently inadequate for that
purpose. If design drawings were sufficiently complete and
adequate for construction, there would be no need for the
general contractor. The architect would be providing the
plan for putting the work in place. The manufacturer and
model along with the precise specifications and physical
characteristics of all products and systems in the building
would be known and detailed in the drawings in advance. In
developing "a complete set of instructions for building
the building" the architect would already have determined
the means and methods for placing the work. There would be
no submittals because all data would be fully anticipated
and addressed in the contract documents. There would be no
RFIs, no ASIs, and much less correspondence overall.
Moreover, project costs would likely increase due to the
absence of competition.
While the Building Information Model may improve the
coordination process in the future, the need for a
contractor's work plan will never go away. Graphically
illustrated concepts, desires, and intentions will never
precisely match constructed fact. By its very nature, the
construction process requires that someone plan, schedule,
coordinate, and direct the means and methods necessary for
project construction and completion.
Architects will continue to design projects and produce
conceptual drawings for the contractor's use. However,
until the industry acknowledges the need and demands that
contractors plan and coordinate the work, architects will
continue to be prevailed upon to coordinate both the
contractor and the work of the trades. Until owners become
more aware as to the contractor's responsibilities under
the AIA documents, the misguided expectation that the
architect is responsible for coordinating the work will
remain. The legal industry will continue to attempt to hold
the architect's conceptual drawings to shop drawing
standards, and the number of claims against architects will
continue to rise.
James B. Atkins, FAIA, is a principal with HKS in Dallas.
He serves on the AIA Documents Committee and the AIA Risk
Management Committee.
Grant A. Simpson, FAIA, manages project delivery for RTKL
Associates in Dallas. He serves on the AIA's Practice
Management Advisory Group.
The authors write a regular monthly column for
AIArchitect that explores aspects of risk management.
AIArchitect is available at www.aia.org. This article is
intended for general information purposes only and does not
constitute legal advice. The reader should consult with
legal counsel to determine how laws, suggestions and
illustrations apply to specific situations.
Reprinted with permission from May / June 2005 Texas Architect.
© Copyright 2005 by the Texas Society of Architects.
|